# What does the length of defect correction period depend on?

**URL:** <https://reachback.builtintelligence.com/t/what-does-the-length-of-defect-correction-period-depend-on/610>\
**Category:** Testing and Defects\
**Created:** [15 October 2012 11:57 UTC](https://reachback.builtintelligence.com/t/what-does-the-length-of-defect-correction-period-depend-on/610 "2012-10-15T11:57:51Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 11:57 UTC](https://reachback.builtintelligence.com/t/what-does-the-length-of-defect-correction-period-depend-on/610/1 "2012-10-15T11:57:51Z")

</div>

What does the length of defect correction period depend on?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 11:58 UTC](https://reachback.builtintelligence.com/t/what-does-the-length-of-defect-correction-period-depend-on/610/2 "2012-10-15T11:58:04Z")

</div>

It will depend on three factors: how much time is needed to correct the Defect; how urgently the Employer needs the Defect corrected; and how easily the Employer can give access to the Contractor to correct the Defect.