# What are the Prices?

**URL:** https://reachback.builtintelligence.com/t/what-are-the-prices/657
**Category:** NEC3 and NEC4 Contracts
**Created:** [15 October 2012 13:33 UTC](https://reachback.builtintelligence.com/t/what-are-the-prices/657 "2012-10-15T13:33:38Z")
**Posts on this page:** 2
**Page:** 1

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 13:33 UTC](https://reachback.builtintelligence.com/t/what-are-the-prices/657/1 "2012-10-15T13:33:38Z")

</div>

What are the Prices?

---

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 13:33 UTC](https://reachback.builtintelligence.com/t/what-are-the-prices/657/2 "2012-10-15T13:33:50Z")

</div>

The Prices are the lump sum prices for each of the activities on the Activity Schedule unless later changed in accordance with this contract (11.2(30)).