# What are the main duties of contractors under the CDM Regulations?

**URL:** <https://reachback.builtintelligence.com/t/what-are-the-main-duties-of-contractors-under-the-cdm-regulations/1349>\
**Category:** CDM\
**Created:** [13 January 2013 10:11 UTC](https://reachback.builtintelligence.com/t/what-are-the-main-duties-of-contractors-under-the-cdm-regulations/1349 "2013-01-13T10:11:06Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [13 January 2013 10:11 UTC](https://reachback.builtintelligence.com/t/what-are-the-main-duties-of-contractors-under-the-cdm-regulations/1349/1 "2013-01-13T10:11:06Z")

</div>



---

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [24 January 2013 13:15 UTC](https://reachback.builtintelligence.com/t/what-are-the-main-duties-of-contractors-under-the-cdm-regulations/1349/2 "2013-01-24T13:15:42Z")

</div>

Contractors must co-operate with each other and with the principal contractor to co-ordinate their work activities. (This applies to adjoining sites as well as the project they are directly involved in.) Contractors should be competent for the work they are doing; plan, manage and monitor their own work to ensure health and safety; and provide suitable information and training for their workers to ensure their health and safety.