# What are formula claims?

**URL:** <https://reachback.builtintelligence.com/t/what-are-formula-claims/1578>\
**Category:** Contractor Claims\
**Created:** [18 January 2013 11:08 UTC](https://reachback.builtintelligence.com/t/what-are-formula-claims/1578 "2013-01-18T11:08:06Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Legal\_Expert](https://avatars.discourse-cdn.com/v4/letter/l/7cd45c/32.png) [@Legal\_Expert](https://reachback.builtintelligence.com/u/Legal_Expert)\
**Post date:** [18 January 2013 11:08 UTC](https://reachback.builtintelligence.com/t/what-are-formula-claims/1578/1 "2013-01-18T11:08:06Z")

</div>



---

<div class="post-metadata">

**Author:** ![Legal\_Expert](https://avatars.discourse-cdn.com/v4/letter/l/7cd45c/32.png) [@Legal\_Expert](https://reachback.builtintelligence.com/u/Legal_Expert)\
**Post date:** [18 January 2013 11:08 UTC](https://reachback.builtintelligence.com/t/what-are-formula-claims/1578/2 "2013-01-18T11:08:41Z")

</div>

Formula claims stem from contractual provisions which entitle the contractor to an increase due to inflation, based upon the terms of the contract. These provide protection and comfort to the contractor in the event of cost increases. They can be included and can sometimes be overlooked.