# What about larger projects? Surely these are too complex for clients to know what is needed?

**URL:** <https://reachback.builtintelligence.com/t/what-about-larger-projects-surely-these-are-too-complex-for-clients-to-know-what-is-needed/1310>\
**Category:** CDM\
**Created:** [13 January 2013 09:51 UTC](https://reachback.builtintelligence.com/t/what-about-larger-projects-surely-these-are-too-complex-for-clients-to-know-what-is-needed/1310 "2013-01-13T09:51:28Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [13 January 2013 09:51 UTC](https://reachback.builtintelligence.com/t/what-about-larger-projects-surely-these-are-too-complex-for-clients-to-know-what-is-needed/1310/1 "2013-01-13T09:51:28Z")

</div>



---

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [24 January 2013 13:42 UTC](https://reachback.builtintelligence.com/t/what-about-larger-projects-surely-these-are-too-complex-for-clients-to-know-what-is-needed/1310/2 "2013-01-24T13:42:52Z")

</div>

For projects lasting longer than 30 days, or involving more than 500 person days of construction work, clients must appoint a CDM co-ordinator. Their primary function is to advise the client. The CDM co-ordinator will be able to advise the client on the appointment of competent dutyholders – assessing the adequacy of other team members’ management arrangements for the project, and the adequacy of the health and safety plan. The client is entitled to rely on the advice of the CDM co-ordinator when making their judgements.