# Weather prevented TM going out

**URL:** <https://reachback.builtintelligence.com/t/weather-prevented-tm-going-out/19654>\
**Category:** Compensation Events\
**Created:** [31 January 2023 08:49 UTC](https://reachback.builtintelligence.com/t/weather-prevented-tm-going-out/19654 "2023-01-31T08:49:20Z")\
**Posts on this page:** 6\
**Page:** 1

<div class="post-metadata">

**Author:** ![KF1000](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/kf1000/32/1220_2.png) [@KF1000](https://reachback.builtintelligence.com/u/KF1000)\
**Post date:** [31 January 2023 08:49 UTC](https://reachback.builtintelligence.com/t/weather-prevented-tm-going-out/19654/1 "2023-01-31T08:49:20Z")

</div>

Due to heavy rainfall the Traffic Management could not go out on a night shift.  
The Subcontractor, who is on an NEC4 Option B, and is claiming a Compensation Event against 60.1, that the Contractor does not allow access.  
They have the same standard weather clauses 60.1(13) for a 1 in 10 year issue.  
Is my colleague correct in rejecting the CE?  
They also notified nearly 9 weeks later, which i believe also could time bar them under cl 61.3, which states they must notify within 7 weeks?

---

<div class="post-metadata">

**Author:** ![QS007](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/qs007/32/173_2.png) [@QS007](https://reachback.builtintelligence.com/u/QS007)\
**Post date:** [31 January 2023 11:34 UTC](https://reachback.builtintelligence.com/t/weather-prevented-tm-going-out/19654/2 "2023-01-31T11:34:24Z")

</div>

My first question to the TM company would be, how has the Contractor not allowed access ? That said, you should be doing your due diligence and impartially assessing whether this is a Compensation Event under your contract.

If a 1 in 10 year event has happened, then you should be accepting the Compensation Event as 60.1 (13).

Re. Time Barr, If the event has happened, and can be demonstrated as happening more than than 7 weeks, you would be able to reject the Compensation Event - ‘has not been notified within the timescales set out in these conditions of subcontract’

---

<div class="post-metadata">

**Author:** ![dave\_bates](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/dave_bates/32/55_2.png) [@dave\_bates](https://reachback.builtintelligence.com/u/dave_bates)\
**Post date:** [2 February 2023 20:02 UTC](https://reachback.builtintelligence.com/t/weather-prevented-tm-going-out/19654/3 "2023-02-02T20:02:54Z")

</div>

Hi I think the CE would stand (if it was a CE) but the assessment would be no change to the Prices and no change to the Completion Date.

---

<div class="post-metadata">

**Author:** ![Neil\_Earnshaw](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/neil_earnshaw/32/515_2.png) [@Neil\_Earnshaw](https://reachback.builtintelligence.com/u/Neil_Earnshaw)\
**Post date:** [13 February 2023 13:01 UTC](https://reachback.builtintelligence.com/t/weather-prevented-tm-going-out/19654/4 "2023-02-13T13:01:21Z")

</div>

I don’t see how the Subcontractor can claim heavy rain on its own is the Contractor not providing access and use in accordance with 33.1? My question is did the Contractor prevent the Subcontractor from having access and use? If not then there’s no grounds for a CE on this basis.

Also weather CE’s are data driven and based on calendar months so it doesn’t matter what happened on one particular day / night of the month, it’s the cumulative rainfall or number of days with rainfall more than 5mm in the month that is used to determine if there is a CE or not.

Finally, due to the above, the 7 week time bar for a weather related CE couldn’t have started from the night shift in question as the Subcontractor couldn’t have been aware that the heavy rain on that night would have meant the threshold for the month was going to be exceeded. This would surely happen the month afterwards when the Subcontractor could obtain the data to see if a CE had or had not been triggered in the month before. If however the CE is not weather related then the 7 weeks would probably start from when the Subcontractor was aware that the traffic management could not be put out, but counting the 7 weeks from the day after the shift in question.

---

<div class="post-metadata">

**Author:** ![Andrew\_W-I](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/andrew_w-i/32/151_2.png) [@Andrew\_W-I](https://reachback.builtintelligence.com/u/Andrew_W-I)\
**Post date:** [13 February 2023 15:28 UTC](https://reachback.builtintelligence.com/t/weather-prevented-tm-going-out/19654/5 "2023-02-13T15:28:41Z")

</div>

Depending upon how the BoQ has been measured, it may be that the Subcontractor can notify this event under clause 60.4, or 60.5, instead. There could, however, still be an issue regarding ‘timing of notification’ under clause 61.3.

---

<div class="post-metadata">

**Author:** ![jpgarvin](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jpgarvin/32/1412_2.png) [@jpgarvin](https://reachback.builtintelligence.com/u/jpgarvin)\
**Post date:** [21 July 2023 23:23 UTC](https://reachback.builtintelligence.com/t/weather-prevented-tm-going-out/19654/6 "2023-07-21T23:23:09Z")

</div>

Hi

The weather clause would only apply if the subcontractor called off the work due to excessive rain

If the Contractor instructed the subcontractor not to do the work then it’s a CE under 60.1 - changed works information to prevent works on that date

The contractor would hope to recover the cost if the rain was sufficiently bad as to trigger the weather clause.

If the contractor didn’t instruct in writing then the subcontractor can only rely on the weather clause (because instructions have to be in writing) and would now be time barred (if he notified late).

If the contractor issued an instruction to close the site in writing and has realised he was wrong to do so (because he can’t recover from the employer) he cannot now pretend that the instruction wasn’t an instruction
