# Under the existing procurement regulations, can deadlines be shortened with electronic publication?

**URL:** <https://reachback.builtintelligence.com/t/under-the-existing-procurement-regulations-can-deadlines-be-shortened-with-electronic-publication/3019>\
**Category:** Procurement\
**Created:** [22 February 2013 16:55 UTC](https://reachback.builtintelligence.com/t/under-the-existing-procurement-regulations-can-deadlines-be-shortened-with-electronic-publication/3019 "2013-02-22T16:55:19Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![CIPS\_Expert](https://avatars.discourse-cdn.com/v4/letter/c/51bf81/32.png) [@CIPS\_Expert](https://reachback.builtintelligence.com/u/CIPS_Expert)\
**Post date:** [22 February 2013 16:55 UTC](https://reachback.builtintelligence.com/t/under-the-existing-procurement-regulations-can-deadlines-be-shortened-with-electronic-publication/3019/1 "2013-02-22T16:55:19Z")

</div>



---

<div class="post-metadata">

**Author:** ![CIPS\_Expert](https://avatars.discourse-cdn.com/v4/letter/c/51bf81/32.png) [@CIPS\_Expert](https://reachback.builtintelligence.com/u/CIPS_Expert)\
**Post date:** [22 February 2013 16:55 UTC](https://reachback.builtintelligence.com/t/under-the-existing-procurement-regulations-can-deadlines-be-shortened-with-electronic-publication/3019/2 "2013-02-22T16:55:27Z")

</div>

Should a contract notice be dispatched to the Official Journal of the European Union then seven days can be deducted from the standard timescales and five days when accelerated procedures are being operated.