# Ukraine War and CE's

**URL:** <https://reachback.builtintelligence.com/t/ukraine-war-and-ces/20967>\
**Category:** Secondary X, W and Y options\
**Created:** [6 July 2023 16:01 UTC](https://reachback.builtintelligence.com/t/ukraine-war-and-ces/20967 "2023-07-06T16:01:13Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![PM10101](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/pm10101/32/94_2.png) [@PM10101](https://reachback.builtintelligence.com/u/PM10101)\
**Post date:** [6 July 2023 16:01 UTC](https://reachback.builtintelligence.com/t/ukraine-war-and-ces/20967/1 "2023-07-06T16:01:13Z")

</div>

I’m working with a Contractor team on an NEC contract which started 2019…In the experience of users of Reachback, are there many live contracts where a compensation event related to X2 change in the law has been accepted wrt the Ukraine War…I understand that a primary route for recovery would be X1, but if this secondary option isn’t selected, has there been any resistance from project managers to the X2 route…

---

<div class="post-metadata">

**Author:** ![S\_Gowdy](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/s_gowdy/32/143_2.png) [@S\_Gowdy](https://reachback.builtintelligence.com/u/S_Gowdy)\
**Post date:** [6 July 2023 19:37 UTC](https://reachback.builtintelligence.com/t/ukraine-war-and-ces/20967/2 "2023-07-06T19:37:07Z")

</div>

Demonstrating a CE under X2 re. the Ukraine war would require the Contractor to firstly identify specific changes in the law and secondly to prove that these particular changes in the law, as opposed to the Ukraine war in general, resulted in additional costs or delay.  
This is a difficult task in my opinion and not something that I have seen accepted - although it would be interesting to hear other peoples experiences.