Time bar on compensation event during furlough period

Can a contractor be time barred from notifying a comp event under clause (14) even if the construction team were furloughed at the time. If not does the 8 weeks notification period start from their return?

Yes, the Contractor should have realised that they needed some staff to remain working to monitor the contract.