# There has been a dispute about the Project Manager or Supervisor not having taken an action. Which Party may refer the dispute to the Adjudicator?

**URL:** <https://reachback.builtintelligence.com/t/there-has-been-a-dispute-about-the-project-manager-or-supervisor-not-having-taken-an-action-which-party-may-refer-the-dispute-to-the-adjudicator/792>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [15 October 2012 18:18 UTC](https://reachback.builtintelligence.com/t/there-has-been-a-dispute-about-the-project-manager-or-supervisor-not-having-taken-an-action-which-party-may-refer-the-dispute-to-the-adjudicator/792 "2012-10-15T18:18:06Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 18:18 UTC](https://reachback.builtintelligence.com/t/there-has-been-a-dispute-about-the-project-manager-or-supervisor-not-having-taken-an-action-which-party-may-refer-the-dispute-to-the-adjudicator/792/1 "2012-10-15T18:18:06Z")

</div>

There has been a dispute about the Project Manager or Supervisor not having taken an action. Which Party may refer the dispute to the Adjudicator?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [15 October 2012 18:18 UTC](https://reachback.builtintelligence.com/t/there-has-been-a-dispute-about-the-project-manager-or-supervisor-not-having-taken-an-action-which-party-may-refer-the-dispute-to-the-adjudicator/792/2 "2012-10-15T18:18:23Z")

</div>

The Contractor may refer the dispute to the Adjudicator (see Adjudication table W1.3).