# There has been a dispute about a quotation for a compensation event which is treated as having been accepted. Which Party may refer the dispute to the Adjudicator?

**URL:** https://reachback.builtintelligence.com/t/there-has-been-a-dispute-about-a-quotation-for-a-compensation-event-which-is-treated-as-having-been-accepted-which-party-may-refer-the-dispute-to-the-adjudicator/794
**Category:** NEC3 and NEC4 Contracts
**Created:** [15 October 2012 18:19 UTC](https://reachback.builtintelligence.com/t/there-has-been-a-dispute-about-a-quotation-for-a-compensation-event-which-is-treated-as-having-been-accepted-which-party-may-refer-the-dispute-to-the-adjudicator/794 "2012-10-15T18:19:33Z")
**Posts on this page:** 2
**Page:** 1

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 18:19 UTC](https://reachback.builtintelligence.com/t/there-has-been-a-dispute-about-a-quotation-for-a-compensation-event-which-is-treated-as-having-been-accepted-which-party-may-refer-the-dispute-to-the-adjudicator/794/1 "2012-10-15T18:19:33Z")

</div>

There has been a dispute about a quotation for a compensation event which is treated as having been accepted. Which Party may refer the dispute to the Adjudicator?

---

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 18:19 UTC](https://reachback.builtintelligence.com/t/there-has-been-a-dispute-about-a-quotation-for-a-compensation-event-which-is-treated-as-having-been-accepted-which-party-may-refer-the-dispute-to-the-adjudicator/794/2 "2012-10-15T18:19:45Z")

</div>

The Employer may refer the dispute to the Adjudicator (see Adjudication table W1.3).