# The Supervisor may instruct the Contractor to search for a Defect until when?

**URL:** <https://reachback.builtintelligence.com/t/the-supervisor-may-instruct-the-contractor-to-search-for-a-defect-until-when/595>\
**Category:** Testing and Defects\
**Created:** [14 October 2012 19:52 UTC](https://reachback.builtintelligence.com/t/the-supervisor-may-instruct-the-contractor-to-search-for-a-defect-until-when/595 "2012-10-14T19:52:36Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:52 UTC](https://reachback.builtintelligence.com/t/the-supervisor-may-instruct-the-contractor-to-search-for-a-defect-until-when/595/1 "2012-10-14T19:52:36Z")

</div>

The Supervisor may instruct the Contractor to search for a Defect until when?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [14 October 2012 19:53 UTC](https://reachback.builtintelligence.com/t/the-supervisor-may-instruct-the-contractor-to-search-for-a-defect-until-when/595/2 "2012-10-14T19:53:03Z")

</div>

Until the defects date (see Clause 42.1).