# The Supervisor has instructed the Contractor to search for a defect and no defect is found. Is this a compensation event?

**URL:** <https://reachback.builtintelligence.com/t/the-supervisor-has-instructed-the-contractor-to-search-for-a-defect-and-no-defect-is-found-is-this-a-compensation-event/157>\
**Category:** Compensation Events\
**Created:** [10 October 2012 12:36 UTC](https://reachback.builtintelligence.com/t/the-supervisor-has-instructed-the-contractor-to-search-for-a-defect-and-no-defect-is-found-is-this-a-compensation-event/157 "2012-10-10T12:36:23Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [10 October 2012 12:36 UTC](https://reachback.builtintelligence.com/t/the-supervisor-has-instructed-the-contractor-to-search-for-a-defect-and-no-defect-is-found-is-this-a-compensation-event/157/1 "2012-10-10T12:36:23Z")

</div>

The Supervisor has instructed the Contractor to search for a defect and no defect is found. Is this a compensation event?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [10 October 2012 12:36 UTC](https://reachback.builtintelligence.com/t/the-supervisor-has-instructed-the-contractor-to-search-for-a-defect-and-no-defect-is-found-is-this-a-compensation-event/157/2 "2012-10-10T12:36:41Z")

</div>

Until the defects date, the Supervisor may instruct the Contractor to search for a Defect (see Clause 42.1). If no defect is found and the Contractor has given sufficient notice of doing work obstructing a required test or inspection, then the event is a compensation event (see Clause 60.1 (10)).