# The Supervisor has instructed the Contractor to search for a defect and no defect is found but the search is needed only because the Contractor gave insufficient notice of doing work obstructing a required test or inspection. Is this a compensation event?

**URL:** <https://reachback.builtintelligence.com/t/the-supervisor-has-instructed-the-contractor-to-search-for-a-defect-and-no-defect-is-found-but-the-search-is-needed-only-because-the-contractor-gave-insufficient-notice-of-doing-work-obstructing-a-required-test-or-inspection-is-this-a-compensation-event/158>\
**Category:** Compensation Events\
**Created:** [10 October 2012 12:37 UTC](https://reachback.builtintelligence.com/t/the-supervisor-has-instructed-the-contractor-to-search-for-a-defect-and-no-defect-is-found-but-the-search-is-needed-only-because-the-contractor-gave-insufficient-notice-of-doing-work-obstructing-a-required-test-or-inspection-is-this-a-compensation-event/158 "2012-10-10T12:37:22Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [10 October 2012 12:37 UTC](https://reachback.builtintelligence.com/t/the-supervisor-has-instructed-the-contractor-to-search-for-a-defect-and-no-defect-is-found-but-the-search-is-needed-only-because-the-contractor-gave-insufficient-notice-of-doing-work-obstructing-a-required-test-or-inspection-is-this-a-compensation-event/158/1 "2012-10-10T12:37:22Z")

</div>

The Supervisor has instructed the Contractor to search for a defect and no defect is found but the search is needed only because the Contractor gave insufficient notice of doing work obstructing a required test or inspection. Is this a compensation event?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [10 October 2012 12:37 UTC](https://reachback.builtintelligence.com/t/the-supervisor-has-instructed-the-contractor-to-search-for-a-defect-and-no-defect-is-found-but-the-search-is-needed-only-because-the-contractor-gave-insufficient-notice-of-doing-work-obstructing-a-required-test-or-inspection-is-this-a-compensation-event/158/2 "2012-10-10T12:37:40Z")

</div>

The event is not a compensation event (see Clause 60.1(10)).