# The Project Manager or Supervisor has given an instruction for dealing with an object of value or of historical or other interest found within the Site. Is this a compensation event?

**URL:** <https://reachback.builtintelligence.com/t/the-project-manager-or-supervisor-has-given-an-instruction-for-dealing-with-an-object-of-value-or-of-historical-or-other-interest-found-within-the-site-is-this-a-compensation-event/154>\
**Category:** Compensation Events\
**Created:** [10 October 2012 12:33 UTC](https://reachback.builtintelligence.com/t/the-project-manager-or-supervisor-has-given-an-instruction-for-dealing-with-an-object-of-value-or-of-historical-or-other-interest-found-within-the-site-is-this-a-compensation-event/154 "2012-10-10T12:33:38Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [10 October 2012 12:33 UTC](https://reachback.builtintelligence.com/t/the-project-manager-or-supervisor-has-given-an-instruction-for-dealing-with-an-object-of-value-or-of-historical-or-other-interest-found-within-the-site-is-this-a-compensation-event/154/1 "2012-10-10T12:33:38Z")

</div>

The Project Manager or Supervisor has given an instruction for dealing with an object of value or of historical or other interest found within the Site. Is this a compensation event?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [10 October 2012 12:33 UTC](https://reachback.builtintelligence.com/t/the-project-manager-or-supervisor-has-given-an-instruction-for-dealing-with-an-object-of-value-or-of-historical-or-other-interest-found-within-the-site-is-this-a-compensation-event/154/2 "2012-10-10T12:33:58Z")

</div>

This is a compensation event (see Clause 60.1(7)). The Contractor notifies the Project Manager of the event as a compensation event. The procedure for dealing with objects of value or historical or other interest found within the Site is stated in Clause 73.1.