# The Project Manager or Supervisor has changed a decision which he has previously communicated to the Contractor. Is this a compensation event?

**URL:** <https://reachback.builtintelligence.com/t/the-project-manager-or-supervisor-has-changed-a-decision-which-he-has-previously-communicated-to-the-contractor-is-this-a-compensation-event/155>\
**Category:** Compensation Events\
**Created:** [10 October 2012 12:34 UTC](https://reachback.builtintelligence.com/t/the-project-manager-or-supervisor-has-changed-a-decision-which-he-has-previously-communicated-to-the-contractor-is-this-a-compensation-event/155 "2012-10-10T12:34:33Z")\
**Posts on this page:** 1\
**Showing post:** 2

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [10 October 2012 12:34 UTC](https://reachback.builtintelligence.com/t/the-project-manager-or-supervisor-has-changed-a-decision-which-he-has-previously-communicated-to-the-contractor-is-this-a-compensation-event/155/2 "2012-10-10T12:34:50Z")

</div>

This is a compensation event (see Clause 60.1(8)). The Contractor notifies the Project Manager of the event as a compensation event.

---