# The Project Manager has instructed the Contractor to stop or not start any substantial work or all work. Can the Contractor terminate?

**URL:** <https://reachback.builtintelligence.com/t/the-project-manager-has-instructed-the-contractor-to-stop-or-not-start-any-substantial-work-or-all-work-can-the-contractor-terminate/313>\
**Category:** Termination\
**Created:** [12 October 2012 10:49 UTC](https://reachback.builtintelligence.com/t/the-project-manager-has-instructed-the-contractor-to-stop-or-not-start-any-substantial-work-or-all-work-can-the-contractor-terminate/313 "2012-10-12T10:49:30Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 10:49 UTC](https://reachback.builtintelligence.com/t/the-project-manager-has-instructed-the-contractor-to-stop-or-not-start-any-substantial-work-or-all-work-can-the-contractor-terminate/313/1 "2012-10-12T10:49:30Z")

</div>

The Project Manager has instructed the Contractor to stop or not start any substantial work or all work. Can the Contractor terminate?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 10:49 UTC](https://reachback.builtintelligence.com/t/the-project-manager-has-instructed-the-contractor-to-stop-or-not-start-any-substantial-work-or-all-work-can-the-contractor-terminate/313/2 "2012-10-12T10:49:47Z")

</div>

The Contractor may terminate if:

```
	the instruction was due to a default by the Employer and

	an instruction allowing the work to restart or start has not been given within thirteen weeks (see Clause 91.6 R19).

If neither Party was culpable for the instruction to stop work, either Party may terminate (R20 Clause 91.6).
```