# The Contractor has terminated because the Employer has had a receiver appointed over its undertaking or assets (R9). What is the termination procedure?

**URL:** <https://reachback.builtintelligence.com/t/the-contractor-has-terminated-because-the-employer-has-had-a-receiver-appointed-over-its-undertaking-or-assets-r9-what-is-the-termination-procedure/379>\
**Category:** Termination\
**Created:** [12 October 2012 13:42 UTC](https://reachback.builtintelligence.com/t/the-contractor-has-terminated-because-the-employer-has-had-a-receiver-appointed-over-its-undertaking-or-assets-r9-what-is-the-termination-procedure/379 "2012-10-12T13:42:45Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 13:42 UTC](https://reachback.builtintelligence.com/t/the-contractor-has-terminated-because-the-employer-has-had-a-receiver-appointed-over-its-undertaking-or-assets-r9-what-is-the-termination-procedure/379/1 "2012-10-12T13:42:45Z")

</div>

The Contractor has terminated because the Employer is a company or partnership and has had a receiver, receiver and manager, or administrative receiver appointed over the whole or a substantial part of its undertaking or assets (R9). What is the termination procedure?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 13:43 UTC](https://reachback.builtintelligence.com/t/the-contractor-has-terminated-because-the-employer-has-had-a-receiver-appointed-over-its-undertaking-or-assets-r9-what-is-the-termination-procedure/379/2 "2012-10-12T13:43:02Z")

</div>

The Parties follow the procedures outlined in P1 and P4 (Clause 92.1). I.e. the Employer may finish the works and can use any Plant and Materials which he has title to and the Contractor leaves the Working Areas and removes the Equipment.