# The Contractor has become aware of an ambiguity in the documents which are part of this contract. What should he do?

**URL:** <https://reachback.builtintelligence.com/t/the-contractor-has-become-aware-of-an-ambiguity-in-the-documents-which-are-part-of-this-contract-what-should-he-do/463>\
**Category:** General\
**Created:** [12 October 2012 16:42 UTC](https://reachback.builtintelligence.com/t/the-contractor-has-become-aware-of-an-ambiguity-in-the-documents-which-are-part-of-this-contract-what-should-he-do/463 "2012-10-12T16:42:50Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 16:42 UTC](https://reachback.builtintelligence.com/t/the-contractor-has-become-aware-of-an-ambiguity-in-the-documents-which-are-part-of-this-contract-what-should-he-do/463/1 "2012-10-12T16:42:50Z")

</div>

The Contractor has become aware of an ambiguity or inconsistency in or between the documents which are part of this contract. What should he do?

---

<div class="post-metadata">

**Author:** ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)\
**Post date:** [12 October 2012 16:43 UTC](https://reachback.builtintelligence.com/t/the-contractor-has-become-aware-of-an-ambiguity-in-the-documents-which-are-part-of-this-contract-what-should-he-do/463/2 "2012-10-12T16:43:03Z")

</div>

As stated in Clause 17.1, on becoming aware of an inconsistency or ambiguity in the documents which are part of the contract, the Contractor should immediately notify the Project Manager.