# Supply Contract - TQs covered in a previous CE

**URL:** <https://reachback.builtintelligence.com/t/supply-contract-tqs-covered-in-a-previous-ce/22686>\
**Category:** Uncategorized\
**Created:** [17 November 2026 17:41 UTC](https://reachback.builtintelligence.com/t/supply-contract-tqs-covered-in-a-previous-ce/22686 "2026-11-17T17:41:34Z")\
**Posts on this page:** 1\
**Page:** 1

<div class="post-metadata">

**Author:** ![johnahoughton](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/johnahoughton/32/1809_2.png) [@johnahoughton](https://reachback.builtintelligence.com/u/johnahoughton)\
**Post date:** [17 November 2026 17:41 UTC](https://reachback.builtintelligence.com/t/supply-contract-tqs-covered-in-a-previous-ce/22686/1 "2026-11-17T17:41:34Z")

</div>

Supplier recovered costs for resolving TQs under a CE. The CE was implemented on CEMAR.

2 years later they are seeking to add costs. They have raised a new CE which we somehow accepted and they are looking to recover costs which should have been included in the original CE 2 years ago. They were actually aware of these additional costs 2 years ago at the time of the original CE. This latest CE specifically cross references the TQs included in the previously agreed CE.

My intention is to reject the latest CE.

Am I missing something?