# Should the Project Manager correct mistakes in the Bill of Quantities?

**URL:** https://reachback.builtintelligence.com/t/should-the-project-manager-correct-mistakes-in-the-bill-of-quantities/688
**Category:** NEC3 and NEC4 Contracts
**Created:** [15 October 2012 14:06 UTC](https://reachback.builtintelligence.com/t/should-the-project-manager-correct-mistakes-in-the-bill-of-quantities/688 "2012-10-15T14:06:28Z")
**Posts on this page:** 2
**Page:** 1

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 14:06 UTC](https://reachback.builtintelligence.com/t/should-the-project-manager-correct-mistakes-in-the-bill-of-quantities/688/1 "2012-10-15T14:06:28Z")

</div>

Should the Project Manager correct mistakes in the Bill of Quantities?

---

<div class="post-metadata">

### Author: ![BuiltIntelligence](https://avatars.discourse-cdn.com/v4/letter/b/919ad9/32.png) [@BuiltIntelligence](https://reachback.builtintelligence.com/u/BuiltIntelligence)
#### Post date: [15 October 2012 14:06 UTC](https://reachback.builtintelligence.com/t/should-the-project-manager-correct-mistakes-in-the-bill-of-quantities/688/2 "2012-10-15T14:06:46Z")

</div>

The Project Manager corrects mistakes in the Bill of Quantities which are departures from the rules for item descriptions and for division of the work into items in the method of measurement or are due to ambiguities or inconsistencies (see Clause 60.6).