# Should the CDM co-ordinator monitor site conditions?

**URL:** <https://reachback.builtintelligence.com/t/should-the-cdm-co-ordinator-monitor-site-conditions/1326>\
**Category:** CDM\
**Created:** [13 January 2013 09:58 UTC](https://reachback.builtintelligence.com/t/should-the-cdm-co-ordinator-monitor-site-conditions/1326 "2013-01-13T09:58:54Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [13 January 2013 09:58 UTC](https://reachback.builtintelligence.com/t/should-the-cdm-co-ordinator-monitor-site-conditions/1326/1 "2013-01-13T09:58:54Z")

</div>



---

<div class="post-metadata">

**Author:** ![HSE](https://avatars.discourse-cdn.com/v4/letter/h/e95f7d/32.png) [@HSE](https://reachback.builtintelligence.com/u/HSE)\
**Post date:** [24 January 2013 13:33 UTC](https://reachback.builtintelligence.com/t/should-the-cdm-co-ordinator-monitor-site-conditions/1326/2 "2013-01-24T13:33:14Z")

</div>

No. The Regulations do not require the CDM co-ordinator to assess the performance on site of the principal contractor. The overall responsibility for controlling and monitoring site health and safety standards lies with the principal contractor.