# NEC4 TSC contracts

**URL:** <https://reachback.builtintelligence.com/t/nec4-tsc-contracts/22228>\
**Category:** Payment\
**Tags:** reachback\
**Created:** [1 April 2025 16:03 UTC](https://reachback.builtintelligence.com/t/nec4-tsc-contracts/22228 "2025-04-01T16:03:14Z")\
**Posts on this page:** 3\
**Page:** 1

<div class="post-metadata">

**Author:** ![keith.brown](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/keith.brown/32/1579_2.png) [@keith.brown](https://reachback.builtintelligence.com/u/keith.brown)\
**Post date:** [1 April 2025 16:03 UTC](https://reachback.builtintelligence.com/t/nec4-tsc-contracts/22228/1 "2025-04-01T16:03:14Z")

</div>

You have 3 weeks from AFP date to pay your supplier. Your current contract price is below what is required to pay the AFP, it can take 5-6 to raise a CE, - so therefore you are leaving yourself wide open to having to pay interest on the payment. With who does this shortfall lie ?

---

<div class="post-metadata">

**Author:** ![stevebrownassociates](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/stevebrownassociates/32/61_2.png) [@stevebrownassociates](https://reachback.builtintelligence.com/u/stevebrownassociates)\
**Post date:** [2 April 2025 10:01 UTC](https://reachback.builtintelligence.com/t/nec4-tsc-contracts/22228/2 "2025-04-02T10:01:42Z")

</div>

Hi Keith, firstly I am assuming the following: the contract is NEC4 ECC; the ‘AFP date’ is the assessment date clause 50.1; the Contractor has submitted an application for payment before the assessment date clause 50.2, the amount due is as per clause 50.3, i.e. the PWDD plus/less other amounts and that the PM has made the assessment of the amount due - (which main Option is it?).  
Provided the PM has assessed the amount due correctly interest is not applicable just because there is a difference between the amount due and the ‘contract price’, I don’t understand this part of your query.  
If you can provide more detail and/or correct any of the above I should be able to answer your query more precisely. Happy to discuss.

---

<div class="post-metadata">

**Author:** ![keith.brown](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/keith.brown/32/1579_2.png) [@keith.brown](https://reachback.builtintelligence.com/u/keith.brown)\
**Post date:** [2 April 2025 10:29 UTC](https://reachback.builtintelligence.com/t/nec4-tsc-contracts/22228/3 "2025-04-02T10:29:29Z")

</div>

Hi Steve,

It would be easier to explain this in person.