# NEC4 PSC Option A - Delays / Omissions from Activity Schedule

**URL:** <https://reachback.builtintelligence.com/t/nec4-psc-option-a-delays-omissions-from-activity-schedule/22031>\
**Category:** Compensation Events\
**Created:** [4 December 2024 16:49 UTC](https://reachback.builtintelligence.com/t/nec4-psc-option-a-delays-omissions-from-activity-schedule/22031 "2024-12-04T16:49:39Z")\
**Posts on this page:** 1\
**Page:** 1

<div class="post-metadata">

**Author:** ![nkelly](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/nkelly/32/1441_2.png) [@nkelly](https://reachback.builtintelligence.com/u/nkelly)\
**Post date:** [4 December 2024 16:49 UTC](https://reachback.builtintelligence.com/t/nec4-psc-option-a-delays-omissions-from-activity-schedule/22031/1 "2024-12-04T16:49:39Z")

</div>

We’re currently engaged by a public sector client on a NEC4 PSC Option A contract. Shortly after the contract start date the scope was changed to which a CE was accepted increasing the project value by 30%.

Due to funding issues the project was put on hold for a considerable period (approx. 1 year), however, some additional works separate from the Activity Schedule have now began to materialise which are covered under CEs.

The award of this contract was a considerable undertaking for my company and resulted in the hiring of additional staff/resources to execute - is there anywhere within the contract that allows for CEs due to delays or omissions to Activities in the AS?