# NEC4 Option A -PMA assesments

**URL:** <https://reachback.builtintelligence.com/t/nec4-option-a-pma-assesments/19401>\
**Category:** Compensation Events\
**Created:** [21 December 2022 13:45 UTC](https://reachback.builtintelligence.com/t/nec4-option-a-pma-assesments/19401 "2022-12-21T13:45:52Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![kevin.matthews](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/kevin.matthews/32/1053_2.png) [@kevin.matthews](https://reachback.builtintelligence.com/u/kevin.matthews)\
**Post date:** [21 December 2022 13:45 UTC](https://reachback.builtintelligence.com/t/nec4-option-a-pma-assesments/19401/1 "2022-12-21T13:45:52Z")

</div>

As a contractor under a NEC4 OP A , if we have received a PMA , if the assessment is incorrect and the PM has excluded items that should have been included , can we raise an NCE to cover these elements or what is our recourse under the contract ?

---

<div class="post-metadata">

**Author:** ![Neil\_Earnshaw](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/neil_earnshaw/32/515_2.png) [@Neil\_Earnshaw](https://reachback.builtintelligence.com/u/Neil_Earnshaw)\
**Post date:** [21 December 2022 17:08 UTC](https://reachback.builtintelligence.com/t/nec4-option-a-pma-assesments/19401/2 "2022-12-21T17:08:09Z")

</div>

Sounds like the CE is implemented so unless you can convince the PM to revise the assessment (which they wouldn’t technically be able to under the contract) you could try speaking to the Client about it to see if they will agree to revise it. You have no entitlement to another CE for the same event so you’re only other recourse is Senior Representatives or adjudication.