# Nec3 short schedule of cost components

**URL:** <https://reachback.builtintelligence.com/t/nec3-short-schedule-of-cost-components/17604>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [9 April 2022 14:58 UTC](https://reachback.builtintelligence.com/t/nec3-short-schedule-of-cost-components/17604 "2022-04-09T14:58:43Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![victor.orr16](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/victor.orr16/32/116_2.png) [@victor.orr16](https://reachback.builtintelligence.com/u/victor.orr16)\
**Post date:** [9 April 2022 14:58 UTC](https://reachback.builtintelligence.com/t/nec3-short-schedule-of-cost-components/17604/1 "2022-04-09T14:58:43Z")

</div>

Hi

Does NEC3 TSSC have a short schedule of cost components?

I don’t see one therefore should I just be using the price list in the contract data

---

<div class="post-metadata">

**Author:** ![Neil\_Earnshaw](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/neil_earnshaw/32/515_2.png) [@Neil\_Earnshaw](https://reachback.builtintelligence.com/u/Neil_Earnshaw)\
**Post date:** [25 April 2022 11:15 UTC](https://reachback.builtintelligence.com/t/nec3-short-schedule-of-cost-components/17604/2 "2022-04-25T11:15:28Z")

</div>

No there aren’t schedules of cost components in NEC3 TSC or TSSC. The TSSC does provide a definition of the term Defined Cost though at clause 11.2(2) which should be applied for assessing compensation events.