# NEC3 "final account"

**URL:** <https://reachback.builtintelligence.com/t/nec3-final-account/21410>\
**Category:** NEC3 and NEC4 Contracts\
**Created:** [7 November 2023 12:00 UTC](https://reachback.builtintelligence.com/t/nec3-final-account/21410 "2023-11-07T12:00:19Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![engineering](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/engineering/32/105_2.png) [@engineering](https://reachback.builtintelligence.com/u/engineering)\
**Post date:** [7 November 2023 12:00 UTC](https://reachback.builtintelligence.com/t/nec3-final-account/21410/1 "2023-11-07T12:00:19Z")

</div>

NEC3: Option A.

For issuing the final account on projects: CL.50.1 requires the PM to make assessments of the amount due up to 4 weeks after issuing the Defects Certificate. The Defects Certificate is a fixed time period from Completion, often 52 weeks. Is it fair to state that the correct final account date would be “four weeks after issuing the Defects Certificate” (completion+52weeks+4weeks)? This would take account any charges the PM/Employer incurred for correcting any uncorrected defects by the defects date (i.e. the original Contractor did not correct their own Defect).

---

<div class="post-metadata">

**Author:** ![andy.thompson](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/andy.thompson/32/64_2.png) [@andy.thompson](https://reachback.builtintelligence.com/u/andy.thompson)\
**Post date:** [10 November 2023 14:57 UTC](https://reachback.builtintelligence.com/t/nec3-final-account/21410/2 "2023-11-10T14:57:30Z")

</div>

I’m glad you put final account in some “” because the actual answer is that there is no such thing. There is a final assessment and therefore payment, but you’ll notice the lack of capitals, because that’s not a defined thing, its just the last time any money changes hands.

Turning to the question, we have to think about the defects process. You can notify defects up to the _defects date_. You issue the Defects Certificate on the later of the Defects Date and the end of the last _defect correction period_. So your formula above is only correct if there are no outstanding defects at the _defects date_. Otherwise it is (end of last _defect correction period_ + 4 weeks).