# NEC3 ECS: X16 Retention bond as an alternative to retention?

**URL:** <https://reachback.builtintelligence.com/t/nec3-ecs-x16-retention-bond-as-an-alternative-to-retention/3556>\
**Category:** Secondary X, W and Y options\
**Created:** [18 November 2015 19:32 UTC](https://reachback.builtintelligence.com/t/nec3-ecs-x16-retention-bond-as-an-alternative-to-retention/3556 "2015-11-18T19:32:42Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![system](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/system/32/1709_2.png) [@system](https://reachback.builtintelligence.com/u/system)\
**Post date:** [18 November 2015 19:32 UTC](https://reachback.builtintelligence.com/t/nec3-ecs-x16-retention-bond-as-an-alternative-to-retention/3556/1 "2015-11-18T19:32:42Z")

</div>

Under an ECS option A contract, in relation to X16 (Retention), as a Subcontractor would we be able to offer a “Retention Bond” in an NEC3 ECS Option “A” contract by way of surety as an alternative to the provisions of Clauses X16.1 and X16.2, which have also been supplemented by a requirement for the Contractor to have full beneficial interest in the amount retained, without any fiduciary obligation?

---

<div class="post-metadata">

**Author:** ![Jon\_Broome](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jon_broome/32/192_2.png) [@Jon\_Broome](https://reachback.builtintelligence.com/u/Jon_Broome)\
**Post date:** [19 November 2015 10:38 UTC](https://reachback.builtintelligence.com/t/nec3-ecs-x16-retention-bond-as-an-alternative-to-retention/3556/2 "2015-11-19T10:38:53Z")

</div>

In relation to X16 : retention, the answer is “Yes, sort of” as the wording of these clauses would need to be modified to reflect the details of what you and the Contractor agree.

I suspect the devil will be in the detail of the bond itself.