# NEC3 ECC - Shorter Schedule of Cost Components Percentages

**URL:** <https://reachback.builtintelligence.com/t/nec3-ecc-shorter-schedule-of-cost-components-percentages/6922>\
**Category:** SOCC SSOCC\
**Created:** [20 October 2020 07:56 UTC](https://reachback.builtintelligence.com/t/nec3-ecc-shorter-schedule-of-cost-components-percentages/6922 "2020-10-20T07:56:31Z")\
**Posts on this page:** 1\
**Showing post:** 2

<div class="post-metadata">

**Author:** ![Neil\_Earnshaw](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/neil_earnshaw/32/515_2.png) [@Neil\_Earnshaw](https://reachback.builtintelligence.com/u/Neil_Earnshaw)\
**Post date:** [31 December 2020 10:24 UTC](https://reachback.builtintelligence.com/t/nec3-ecc-shorter-schedule-of-cost-components-percentages/6922/2 "2020-12-31T10:24:38Z")

</div>

Taking each component in turn:

People

- Amount paid by Contractor for Contractor’s people + % people overheads = sub total for Contractor’s people

- Amount paid by Subcontractor for Subcontractor’s people + % people overheads = sub total for Subcontractor’s people

Plant and Materials

- Payments for purchasing Plant and Materials = sub total for Plant and Materials

Design

- (Total hours worked by Subcontractor’s employees x hourly rates in Contract Data) + % design overheads = sub total for design

The direct and subcontracted fee percentages are then applied to the relevant components to arrive at a total, in your case as the fee percentages are the same it doesn’t matter but it would be important to apply it correctly if they were different.

---