We have a subcontract with a surfacing contractor whereby under Data Part 1 it states:
Attendances, if any, for use in common with the Contractor and other sub-contractors: None
Attendances, if any, for the exclusive use of the Subcontractor: None
Subsequently our surfacing contractor is advising that traffic management does not form part of ‘Attendances’ and they are therefore not obliged to supply.
Please can someone advise if there is anywhere that stipulates/defines what falls under the ‘Attendances’ banner ?