# NEC3 ECC: Option A - Activity Schedule

**URL:** <https://reachback.builtintelligence.com/t/nec3-ecc-option-a-activity-schedule/3999>\
**Category:** Payment\
**Created:** [15 March 2017 23:38 UTC](https://reachback.builtintelligence.com/t/nec3-ecc-option-a-activity-schedule/3999 "2017-03-15T23:38:13Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![system](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/system/32/1709_2.png) [@system](https://reachback.builtintelligence.com/u/system)\
**Post date:** [15 March 2017 23:38 UTC](https://reachback.builtintelligence.com/t/nec3-ecc-option-a-activity-schedule/3999/1 "2017-03-15T23:38:13Z")

</div>

If an item of work is included within the Contractors Activity schedule but that item has not been carried out on site; how do we deal with the financial side of this issue:  
a. Presumably it cannot be included in the PWDD  
b. At the end of the job after handover should I include it in the assessment for payment  
or c. The contractor does not get paid at all  
Could you consider this issue if a. it is specifically included within the EMPLOYERS works information b. It is specifically included in the Contractors works information only c. not included in either works information

---

<div class="post-metadata">

**Author:** ![Glenn\_Hide](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/glenn_hide/32/476_2.png) [@Glenn\_Hide](https://reachback.builtintelligence.com/u/Glenn_Hide)\
**Post date:** [15 March 2017 23:45 UTC](https://reachback.builtintelligence.com/t/nec3-ecc-option-a-activity-schedule/3999/2 "2017-03-15T23:45:00Z")

</div>

The Contractor should revise their activity schedule and spread that cost elsewhere within the other items on the activity schedule. It is a lump sum fixed price. If an item is not done it does not mean the Employer does not pay it - likewise if a Contractor does double what they thought of an item on the activity schedule they cant claim extra as a change in activity schedule alone is not a CE.