# NEC3 ECC: Insurance excess

**URL:** <https://reachback.builtintelligence.com/t/nec3-ecc-insurance-excess/3358>\
**Category:** Risk and Insurance\
**Created:** [31 March 2015 20:26 UTC](https://reachback.builtintelligence.com/t/nec3-ecc-insurance-excess/3358 "2015-03-31T20:26:09Z")\
**Posts on this page:** 3\
**Page:** 1

<div class="post-metadata">

**Author:** ![system](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/system/32/1709_2.png) [@system](https://reachback.builtintelligence.com/u/system)\
**Post date:** [31 March 2015 20:26 UTC](https://reachback.builtintelligence.com/t/nec3-ecc-insurance-excess/3358/1 "2015-03-31T20:26:09Z")

</div>

Under ECC Option C, Is the Contractor entitled to claim insurance excess if a claim arises through no fault of the contractor on the original scope of works?

---

<div class="post-metadata">

**Author:** ![Jon\_Broome](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jon_broome/32/192_2.png) [@Jon\_Broome](https://reachback.builtintelligence.com/u/Jon_Broome)\
**Post date:** [7 April 2015 20:58 UTC](https://reachback.builtintelligence.com/t/nec3-ecc-insurance-excess/3358/2 "2015-04-07T20:58:57Z")

</div>

Fault does not come into it. It comes down to risk allocation under the contract. If the Contractor incurs Defined Cost in providing the works even if it is for an insurable event, then at first level, they are reimbursed it. However, under clause 7 of the Schedule of Cost Components, the cost of events for which the Contractor is required to insure are deducted. The excess / deductible is stated in Contract Data Part 1 by the Employer, so the Contractor is reimbursed up to this amount, but then has to bear the remainder of the costs above this amount.

---

<div class="post-metadata">

**Author:** ![Jon\_Broome](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jon_broome/32/192_2.png) [@Jon\_Broome](https://reachback.builtintelligence.com/u/Jon_Broome)\
**Post date:** [8 April 2015 21:31 UTC](https://reachback.builtintelligence.com/t/nec3-ecc-insurance-excess/3358/3 "2015-04-08T21:31:47Z")

</div>

Also clause 85.4 is relevant : “Any amount not recovered from an insurer is borne by the Employer for events which are at his risk and by the Contractor for events which are at his risk.”
