I have noticed that some of the subcontracts which are being issued to subcontractors has the Contractor’s satellite office address detailed with the company registered number next to it. However the satellite office is not the registered office, does this affect the subcontract and are there any implications?
1 Like
Legally, I do not think it does as name of the Contractor and Company Number are the same as the legal entity that is the company.
In terms of operating the contract, the address stated would be the one to which contractual communications should be sent to unless the Subcontractor is notified otherwise - see clause 13.2.