# NEC Option B Prelims (Planned Completion or Contract Completion)

**URL:** <https://reachback.builtintelligence.com/t/nec-option-b-prelims-planned-completion-or-contract-completion/20135>\
**Category:** General\
**Tags:** nec\
**Created:** [21 March 2023 17:19 UTC](https://reachback.builtintelligence.com/t/nec-option-b-prelims-planned-completion-or-contract-completion/20135 "2023-03-21T17:19:09Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Kris](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/kris/32/240_2.png) [@Kris](https://reachback.builtintelligence.com/u/Kris)\
**Post date:** [21 March 2023 17:19 UTC](https://reachback.builtintelligence.com/t/nec-option-b-prelims-planned-completion-or-contract-completion/20135/1 "2023-03-21T17:19:10Z")

</div>

Currently working on a NEC3 Option B contract as the Sub-Contractor.  
Within our B.O.Q we have a seperate section covering the Prelims.  
We currently have a planned completion date with terminal float of 2 weeks. If we where to need this terminal float would our prelims be payable upto the Contract completion date?

---

<div class="post-metadata">

**Author:** ![engineering](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/engineering/32/105_2.png) [@engineering](https://reachback.builtintelligence.com/u/engineering)\
**Post date:** [22 March 2023 13:58 UTC](https://reachback.builtintelligence.com/t/nec-option-b-prelims-planned-completion-or-contract-completion/20135/2 "2023-03-22T13:58:38Z")

</div>

It depends how the BoQ is put together. Your BoQ will be “Quantity x rate”, what is the stated “quantity” for prelims? If there is no extension (via a Compensation Event) then when you reach the final stated quantity the Employer will stop paying you. You would not pay a Contractor extra for their own delay.