# NEC ECSC: Does the Price List form part of the Works Information under Short Form of Contract?

**URL:** https://reachback.builtintelligence.com/t/nec-ecsc-does-the-price-list-form-part-of-the-works-information-under-short-form-of-contract/4368
**Category:** NEC3 and NEC4 Contracts
**Created:** [26 November 2017 19:33 UTC](https://reachback.builtintelligence.com/t/nec-ecsc-does-the-price-list-form-part-of-the-works-information-under-short-form-of-contract/4368 "2017-11-26T19:33:14Z")
**Posts on this page:** 2
**Page:** 1

<div class="post-metadata">

### Author: ![Sean](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/sean/32/143_2.png) [@Sean](https://reachback.builtintelligence.com/u/Sean)
#### Post date: [26 November 2017 19:33 UTC](https://reachback.builtintelligence.com/t/nec-ecsc-does-the-price-list-form-part-of-the-works-information-under-short-form-of-contract/4368/1 "2017-11-26T19:33:14Z")

</div>

The Price List contains specific item descriptions for elements of work which conflicts with the specification document.

Is the Price List part of the Works Information

---

<div class="post-metadata">

### Author: ![Jon\_Broome](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jon_broome/32/192_2.png) [@Jon\_Broome](https://reachback.builtintelligence.com/u/Jon_Broome)
#### Post date: [27 November 2017 12:47 UTC](https://reachback.builtintelligence.com/t/nec-ecsc-does-the-price-list-form-part-of-the-works-information-under-short-form-of-contract/4368/2 "2017-11-27T12:47:33Z")

</div>

The answer is ‘No’.

However, when the Price List is written by the Employer, it is not unusual for there to be a reference to the Price List from the Works Information incoporating the descriptions in it as part of the works. Unfortunately, this is also usually accompanied by a disclaimer saying that if we - the Employer’s consultant - has left anything out causing the Contractor to not price it, then this is at the Contractor’s risk.