# NEC ECS: Sub-subcontractor costs

**URL:** <https://reachback.builtintelligence.com/t/nec-ecs-sub-subcontractor-costs/4155>\
**Category:** Compensation Events\
**Created:** [21 June 2017 18:42 UTC](https://reachback.builtintelligence.com/t/nec-ecs-sub-subcontractor-costs/4155 "2017-06-21T18:42:59Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![system](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/system/32/1709_2.png) [@system](https://reachback.builtintelligence.com/u/system)\
**Post date:** [21 June 2017 18:42 UTC](https://reachback.builtintelligence.com/t/nec-ecs-sub-subcontractor-costs/4155/1 "2017-06-21T18:42:59Z")

</div>

When valuing CE’s which include a sub sub contractors costs, should the sub sub contractors costs be exclusive of their overhead & profit and deemed to be included in the sub contracted fee in the Contract Data Part 2?

---

<div class="post-metadata">

**Author:** ![Jon\_Broome](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jon_broome/32/192_2.png) [@Jon\_Broome](https://reachback.builtintelligence.com/u/Jon_Broome)\
**Post date:** [21 June 2017 20:37 UTC](https://reachback.builtintelligence.com/t/nec-ecs-sub-subcontractor-costs/4155/2 "2017-06-21T20:37:04Z")

</div>

Depends from where you are looking at it from and which option the main Contractor is on, the Subcontractor is on and the sub sub contractor is on ! Please clarify !