# NEC ECS - Different options for correcting a Subcontractor defect

**URL:** <https://reachback.builtintelligence.com/t/nec-ecs-different-options-for-correcting-a-subcontractor-defect/5758>\
**Category:** Testing and Defects\
**Created:** [7 April 2020 15:49 UTC](https://reachback.builtintelligence.com/t/nec-ecs-different-options-for-correcting-a-subcontractor-defect/5758 "2020-04-07T15:49:09Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![peter\_johnson](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/peter_johnson/32/293_2.png) [@peter\_johnson](https://reachback.builtintelligence.com/u/peter_johnson)\
**Post date:** [7 April 2020 15:49 UTC](https://reachback.builtintelligence.com/t/nec-ecs-different-options-for-correcting-a-subcontractor-defect/5758/1 "2020-04-07T15:49:09Z")

</div>

NEC ECS Option A Subcontract.

There is a Defect in a piece of kit that has been installed by our sub-subby.

The Defect has been notified to the sub-subby and to our customer.

There are two ‘options’ for resolving the defect i.e. complete replacement (our preference) or a work-round that would first require a concession from our customer (that we might not get).

Understand that the sub-subby is required to correct the Defect, but how do we explicity tell him to replace the item? Would this be via a Contractor’s Instruction?

---

<div class="post-metadata">

**Author:** ![Neil\_Earnshaw](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/neil_earnshaw/32/515_2.png) [@Neil\_Earnshaw](https://reachback.builtintelligence.com/u/Neil_Earnshaw)\
**Post date:** [7 April 2020 17:09 UTC](https://reachback.builtintelligence.com/t/nec-ecs-different-options-for-correcting-a-subcontractor-defect/5758/2 "2020-04-07T17:09:59Z")

</div>

I would firstly discuss the options with Employer, PM, Supervisor and Subcontractor in the context of a risk reduction meeting (assuming NEC3 ECS) as you are concerned that the Subcontractor’s proposal may “impair the performance of the works in use”.

If the Employer accepts the Subcontractor’s work round proposal then you should allow the Subcontractor to implement it. If the work round doesn’t work then the Subcontractor is still liable to correct the Defect and maybe then it would appropriate to go for complete replacement.

If the Employer doesn’t accept the proposal and the Subcontractor refuses complete replacement, then you could instruct them. Normally that instruction would be a CE however you may be able to reject this under clause 61.4 as “fault of the Subcontractor”. However if the Subcontractor can prove their proposal would work then you and the Employer may have to concede CEs in your contracts if you insist on complete replacement.

Ultimately if the Subcontractor refuses to correct the Defect then clause 45.1 gives you the right to recover the cost of others correcting it and for the Subcontractor to pay this cost.
