# NEC ECS: Agreed reduction for early payment

**URL:** https://reachback.builtintelligence.com/t/nec-ecs-agreed-reduction-for-early-payment/5238
**Category:** Payment
**Created:** [19 August 2019 07:44 UTC](https://reachback.builtintelligence.com/t/nec-ecs-agreed-reduction-for-early-payment/5238 "2019-08-19T07:44:09Z")
**Posts on this page:** 3
**Page:** 1

<div class="post-metadata">

### Author: ![trauts80](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/trauts80/32/302_2.png) [@trauts80](https://reachback.builtintelligence.com/u/trauts80)
#### Post date: [19 August 2019 07:44 UTC](https://reachback.builtintelligence.com/t/nec-ecs-agreed-reduction-for-early-payment/5238/1 "2019-08-19T07:44:09Z")

</div>

We are the MWC and have a Subcontractor under an NEC3 Option A Subcontract.

The Subcontractor asked if we could pay 2 payment certificates at the same time for which they would give us a discount to the Subcontract price.

This has now been agreed and processed but how would we reduce the prices as it’s not a Compensation Event etc.?

---

<div class="post-metadata">

### Author: ![Jon\_Broome](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jon_broome/32/192_2.png) [@Jon\_Broome](https://reachback.builtintelligence.com/u/Jon_Broome)
#### Post date: [19 August 2019 10:18 UTC](https://reachback.builtintelligence.com/t/nec-ecs-agreed-reduction-for-early-payment/5238/2 "2019-08-19T10:18:52Z")

</div>

You have inadvertently modified the contract. To make this legal, you both need to sign - as in directors who would normally sign contracts in order to enter into them - a supplementary agreement confirming this agreement.

---

<div class="post-metadata">

### Author: ![anonymous1](https://avatars.discourse-cdn.com/v4/letter/a/77aa72/32.png) [@anonymous1](https://reachback.builtintelligence.com/u/anonymous1)
#### Post date: [19 August 2019 13:35 UTC](https://reachback.builtintelligence.com/t/nec-ecs-agreed-reduction-for-early-payment/5238/3 "2019-08-19T13:35:50Z")

</div>

Jon is right - but given this is likely to be for a very small amount then you would like to think you can both find a way just by mutual agreement. You could by agreement make it fit a negative CE, or under NEC4 you could use a Contractors proposal equivalent to value engineering.