# NEC ECS: 61.2 Proposed Instruction / Change Decison

**URL:** <https://reachback.builtintelligence.com/t/nec-ecs-61-2-proposed-instruction-change-decison/4683>\
**Category:** Compensation Events\
**Created:** [12 September 2018 08:06 UTC](https://reachback.builtintelligence.com/t/nec-ecs-61-2-proposed-instruction-change-decison/4683 "2018-09-12T08:06:16Z")\
**Posts on this page:** 1\
**Showing post:** 2

<div class="post-metadata">

**Author:** ![Jon\_Broome](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jon_broome/32/192_2.png) [@Jon\_Broome](https://reachback.builtintelligence.com/u/Jon_Broome)\
**Post date:** [12 September 2018 09:39 UTC](https://reachback.builtintelligence.com/t/nec-ecs-61-2-proposed-instruction-change-decison/4683/2 "2018-09-12T09:39:37Z")

</div>

You instructed a quotation for a proposed instruction.

Having received it, you are not responding to it within the contractual timescales of clause 62.3. Consequently - and this would presumably be reinforced by the detail in the quotation - as a (Sub)contractor, I would argue that any acceptance is out of time and not valid. (Note : in NEC4, the issue of proposed instructions has been significantly tidied up in terms of reducing contractual loose ends - see clause 65)

So you start again, either

- instructing the works as a change to the Works with the quotation to follow or
- instruct a revised quotation for a proposed instruction.

---

_[View the full topic](https://reachback.builtintelligence.com/t/nec-ecs-61-2-proposed-instruction-change-decison/4683)._