# NEC ECC: Termination for any reason

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-termination-for-any-reason/4979>\
**Category:** Termination\
**Created:** [13 March 2019 20:13 UTC](https://reachback.builtintelligence.com/t/nec-ecc-termination-for-any-reason/4979 "2019-03-13T20:13:54Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![adon](https://avatars.discourse-cdn.com/v4/letter/a/0ea827/32.png) [@adon](https://reachback.builtintelligence.com/u/adon)\
**Post date:** [13 March 2019 20:13 UTC](https://reachback.builtintelligence.com/t/nec-ecc-termination-for-any-reason/4979/1 "2019-03-13T20:13:54Z")

</div>

Clause 90.1 of the NEC 3 ECC Contact allows an Employer to terminate for any reason. Are there any requirements that they must do so in good faith etc? Or can it be at will for for any reason at all even if it is unfair to the Contractor?

---

<div class="post-metadata">

**Author:** ![Andrew\_W-I](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/andrew_w-i/32/151_2.png) [@Andrew\_W-I](https://reachback.builtintelligence.com/u/Andrew_W-I)\
**Post date:** [14 March 2019 08:03 UTC](https://reachback.builtintelligence.com/t/nec-ecc-termination-for-any-reason/4979/2 "2019-03-14T08:03:20Z")

</div>

It doesn’t expressly state what the reason might be, although it wouldn’t include one of the other specified reasons.

Where the Employer terminates for ‘any (other) reason’ the Contractor is paid amounts due A1 A2 and A4, with A4 essentially including ‘lost profit’, so the Contractor doesn’t ‘lose out’ from whatever reason the Employer has used to terminate.

Whether it is ‘fair’ or not doesn’t take away from the fact that the Employer is entitled to exercise this right under the contract.