# NEC ECC: Retention in Option F

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-retention-in-option-f/5606>\
**Category:** Main options\
**Created:** [10 February 2020 23:06 UTC](https://reachback.builtintelligence.com/t/nec-ecc-retention-in-option-f/5606 "2020-02-10T23:06:37Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Jaime\_Curo](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jaime_curo/32/1355_2.png) [@Jaime\_Curo](https://reachback.builtintelligence.com/u/Jaime_Curo)\
**Post date:** [10 February 2020 23:06 UTC](https://reachback.builtintelligence.com/t/nec-ecc-retention-in-option-f/5606/1 "2020-02-10T23:06:37Z")

</div>

Under option F, what is the retention (clause 24) in Defined Cost referring to? The concept of withholding is similar as retention?

---

<div class="post-metadata">

**Author:** ![Glenn\_Hide](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/glenn_hide/32/476_2.png) [@Glenn\_Hide](https://reachback.builtintelligence.com/u/Glenn_Hide)\
**Post date:** [10 February 2020 23:10 UTC](https://reachback.builtintelligence.com/t/nec-ecc-retention-in-option-f/5606/2 "2020-02-10T23:10:55Z")

</div>

Retention is withheld from a Contractor if X16 retention has been chosen by the Employer.

The clause you highlight in option F is talking about Defined Cost being any payment to Subcontractors, without taking into account amounts deducted for retention within their contract with the Contractor if they have also used X16 with their supply chain.