# NEC ECC: Repairs to temporary works

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-repairs-to-temporary-works/4815>\
**Category:** Compensation Events\
**Created:** [4 December 2018 18:34 UTC](https://reachback.builtintelligence.com/t/nec-ecc-repairs-to-temporary-works/4815 "2018-12-04T18:34:31Z")\
**Posts on this page:** 3\
**Page:** 1

<div class="post-metadata">

**Author:** ![LFS](https://avatars.discourse-cdn.com/v4/letter/l/53a042/32.png) [@LFS](https://reachback.builtintelligence.com/u/LFS)\
**Post date:** [4 December 2018 18:34 UTC](https://reachback.builtintelligence.com/t/nec-ecc-repairs-to-temporary-works/4815/1 "2018-12-04T18:34:31Z")

</div>

An area of temporary works have been constructed under an NEC Option C Contract. There have now been a couple of instances where weather (but not outside of the 10 year average) has damaged the temporary works. Does the Contractor have the obligation to maintain/repair the temporary works or would this constitute a CE under the contract ?

---

<div class="post-metadata">

**Author:** ![Glenn\_Hide](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/glenn_hide/32/476_2.png) [@Glenn\_Hide](https://reachback.builtintelligence.com/u/Glenn_Hide)\
**Post date:** [4 December 2018 18:37 UTC](https://reachback.builtintelligence.com/t/nec-ecc-repairs-to-temporary-works/4815/2 "2018-12-04T18:37:55Z")

</div>

That would be a Contractor risk - and no where under clause 60.1 that the Contractor would be able to notify that as a compensation event I suggest.

---

<div class="post-metadata">

**Author:** ![Jon\_Broome](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jon_broome/32/192_2.png) [@Jon\_Broome](https://reachback.builtintelligence.com/u/Jon_Broome)\
**Post date:** [5 December 2018 09:23 UTC](https://reachback.builtintelligence.com/t/nec-ecc-repairs-to-temporary-works/4815/3 "2018-12-05T09:23:17Z")

</div>

Or more precisely, a risk within the target Prices and, because it is a target cost contract with pain/gain, a shared risk.