# NEC ECC: Option C - Expenses Disallowed

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-option-c-expenses-disallowed/5358>\
**Category:** SOCC SSOCC\
**Created:** [30 October 2019 17:43 UTC](https://reachback.builtintelligence.com/t/nec-ecc-option-c-expenses-disallowed/5358 "2019-10-30T17:43:46Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![peter\_johnson](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/peter_johnson/32/293_2.png) [@peter\_johnson](https://reachback.builtintelligence.com/u/peter_johnson)\
**Post date:** [30 October 2019 17:43 UTC](https://reachback.builtintelligence.com/t/nec-ecc-option-c-expenses-disallowed/5358/1 "2019-10-30T17:43:46Z")

</div>

NEC3 ECC Option C contract.

We are the Contractor and have travel expenses costs (flights etc) that are backed up by invoice evidence.

The client is making his own assessment/disallowing some of these travel costs on the basis that e.g. 'you could have purchased that flight for ‘£200 rather than the £400 you paid’. Can the Client do that?

---

<div class="post-metadata">

**Author:** ![Glenn\_Hide](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/glenn_hide/32/476_2.png) [@Glenn\_Hide](https://reachback.builtintelligence.com/u/Glenn_Hide)\
**Post date:** [30 October 2019 17:48 UTC](https://reachback.builtintelligence.com/t/nec-ecc-option-c-expenses-disallowed/5358/2 "2019-10-30T17:48:55Z")

</div>

Only if they can prove at the time that you could have purchased a comparable flight at the time for £200 (and not a cheap one via Brussels and then Amsterdam before a third stop over in Paris). Probably hard to prove, and you would like to think that you would not have booked a £400 flight when a £200 one was available. If we were talking the difference between 1st and 2nd class then they would have a point, but I assume you are not here.

It is a bit like buying materials for a CE more than at market rates. They could assess it at what would have been open market rates at the time.