# NEC ECC: Option C - Can non-project specifIc training costs be disallowed?

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-option-c-can-non-project-specific-training-costs-be-disallowed/4851>\
**Category:** Main options\
**Created:** [11 January 2019 17:26 UTC](https://reachback.builtintelligence.com/t/nec-ecc-option-c-can-non-project-specific-training-costs-be-disallowed/4851 "2019-01-11T17:26:48Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Emma79](https://avatars.discourse-cdn.com/v4/letter/e/eb9ed0/32.png) [@Emma79](https://reachback.builtintelligence.com/u/Emma79)\
**Post date:** [11 January 2019 17:26 UTC](https://reachback.builtintelligence.com/t/nec-ecc-option-c-can-non-project-specific-training-costs-be-disallowed/4851/1 "2019-01-11T17:26:48Z")

</div>

I am currently the Employer under an NEC3 ECC Option C Contract. The Contractor is required to provide me with a qualified workforce, however, I am in receipt of costs associated with basic training which I would expect a qualified worker to come equip with i.e. the contractor has brought in a team of scaffolders but a number of them have training which is out of date and I am being charged for the renewal, additionally, the Contractor has a number of corporate training requirements (outside of my control) which I am also being charged for. In my view, I would only pay for training costs which were specific to my project environment and could not be transferred or of value outside of my project.

---

<div class="post-metadata">

**Author:** ![Andrew\_W-I](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/andrew_w-i/32/151_2.png) [@Andrew\_W-I](https://reachback.builtintelligence.com/u/Andrew_W-I)\
**Post date:** [14 January 2019 08:17 UTC](https://reachback.builtintelligence.com/t/nec-ecc-option-c-can-non-project-specific-training-costs-be-disallowed/4851/2 "2019-01-14T08:17:07Z")

</div>

To be included as a genuine cost component, the training in question should relate to safety, as per SCC People category 13 (o). Note that the cost must also be incurred in order to Provide the Works, so any general training requirements, such as corporate procedures, would deemed to be included in the Fee.

The simplest way to calculate a cost is to assess the ‘lifecycle’ cost from the date when the training is given to the date when the qualification expires, Calculate the period of time when the person is working on Providing the Works and pro-rata this. Note that some training may be very ‘project specific’ so in these circumstances you would probably negotiate a sensible apportionment of cost.

Option C is intended to cover the ‘cost to employ’, which would include periodic training and renewal of licences, etc, so should be included as part of the assessment, where such costs appropriately fall under a category in the Schedule of Cost Componenets.