# NEC ECC: Is Working Area Overhead a Defined Cost?

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-is-working-area-overhead-a-defined-cost/5412>\
**Category:** SOCC SSOCC\
**Created:** [20 November 2019 18:04 UTC](https://reachback.builtintelligence.com/t/nec-ecc-is-working-area-overhead-a-defined-cost/5412 "2019-11-20T18:04:09Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Hrunner](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/hrunner/32/55_2.png) [@Hrunner](https://reachback.builtintelligence.com/u/Hrunner)\
**Post date:** [20 November 2019 18:04 UTC](https://reachback.builtintelligence.com/t/nec-ecc-is-working-area-overhead-a-defined-cost/5412/1 "2019-11-20T18:04:09Z")

</div>

As per Clause 63.1 under Option C, the change of the prices for a CE are Actual Defined Cost of works already done, the forecast of Defined Cost of the works not yet done and the resulting Fee.

Resulting Fee is calculated in Defined cost to increase the target

Is Fee added to the Working Area Overhead %?. Is the Working area overhead cost a Defined Cost? or is this Fee on Fee??

---

<div class="post-metadata">

**Author:** ![Andrew\_W-I](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/andrew_w-i/32/151_2.png) [@Andrew\_W-I](https://reachback.builtintelligence.com/u/Andrew_W-I)\
**Post date:** [21 November 2019 07:05 UTC](https://reachback.builtintelligence.com/t/nec-ecc-is-working-area-overhead-a-defined-cost/5412/2 "2019-11-21T07:05:45Z")

</div>

Yes, the Working Areas overheads charge is Defined Cost and so the direct fee percentage is applied accordingly.

It is not a case of ‘fee on fee’ as it is essentially a ‘simplified’ way to calculate part of the cost component for Charges.