# NEC ECC: Is there a limit on when a Contractor can go to adjudication?

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-is-there-a-limit-on-when-a-contractor-can-go-to-adjudication/4440>\
**Category:** General\
**Created:** [13 February 2018 14:22 UTC](https://reachback.builtintelligence.com/t/nec-ecc-is-there-a-limit-on-when-a-contractor-can-go-to-adjudication/4440 "2018-02-13T14:22:33Z")\
**Posts on this page:** 5\
**Page:** 1

<div class="post-metadata">

**Author:** ![anonymous1](https://avatars.discourse-cdn.com/v4/letter/a/77aa72/32.png) [@anonymous1](https://reachback.builtintelligence.com/u/anonymous1)\
**Post date:** [13 February 2018 14:22 UTC](https://reachback.builtintelligence.com/t/nec-ecc-is-there-a-limit-on-when-a-contractor-can-go-to-adjudication/4440/1 "2018-02-13T14:22:33Z")

</div>

Can a Contractor go to adjudication after the Defects Certificate/final account has been issued?

---

<div class="post-metadata">

**Author:** ![Andrew\_W-I](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/andrew_w-i/32/151_2.png) [@Andrew\_W-I](https://reachback.builtintelligence.com/u/Andrew_W-I)\
**Post date:** [13 February 2018 14:53 UTC](https://reachback.builtintelligence.com/t/nec-ecc-is-there-a-limit-on-when-a-contractor-can-go-to-adjudication/4440/2 "2018-02-13T14:53:50Z")

</div>

The ‘Construction Act’ provides that a dispute may be referred ‘at any time’ (s108 (2) (a), so the answer is ‘yes’.

---

<div class="post-metadata">

**Author:** ![anonymous1](https://avatars.discourse-cdn.com/v4/letter/a/77aa72/32.png) [@anonymous1](https://reachback.builtintelligence.com/u/anonymous1)\
**Post date:** [13 February 2018 15:24 UTC](https://reachback.builtintelligence.com/t/nec-ecc-is-there-a-limit-on-when-a-contractor-can-go-to-adjudication/4440/3 "2018-02-13T15:24:27Z")

</div>

So is there no limit as to when adjudication can be applied - 5/10 years after project has finished???

---

<div class="post-metadata">

**Author:** ![Rob\_Horne](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/rob_horne/32/200_2.png) [@Rob\_Horne](https://reachback.builtintelligence.com/u/Rob_Horne)\
**Post date:** [13 February 2018 15:26 UTC](https://reachback.builtintelligence.com/t/nec-ecc-is-there-a-limit-on-when-a-contractor-can-go-to-adjudication/4440/4 "2018-02-13T15:26:52Z")

</div>

There are in fact numerous limitations on when an adjudication can be started. The two most relevant here are the limitation act (6 years for a contract or 12 years for a deed) and post final account where there is a conclusivity provision.

The Construction Act only allows for a “dispute or difference” to be referred to adjudication. If the contract contains a provision making something, usually the final account, conclusive, once it has become conclusive you cannot have a dispute and therefore cannot go to adjudication.

---

<div class="post-metadata">

**Author:** ![Rob\_Horne](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/rob_horne/32/200_2.png) [@Rob\_Horne](https://reachback.builtintelligence.com/u/Rob_Horne)\
**Post date:** [13 February 2018 15:27 UTC](https://reachback.builtintelligence.com/t/nec-ecc-is-there-a-limit-on-when-a-contractor-can-go-to-adjudication/4440/5 "2018-02-13T15:27:57Z")

</div>

This is generally correct but there are circumstances where “at any time” doesn’t quite mean that. See my answer below regarding the Limitation Act and conclusive statements.