# NEC ECC: Fail to reply quotation by Project Manager

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-fail-to-reply-quotation-by-project-manager/5604>\
**Category:** Compensation Events\
**Created:** [10 February 2020 12:52 UTC](https://reachback.builtintelligence.com/t/nec-ecc-fail-to-reply-quotation-by-project-manager/5604 "2020-02-10T12:52:18Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![mkd890](https://avatars.discourse-cdn.com/v4/letter/m/ea5d25/32.png) [@mkd890](https://reachback.builtintelligence.com/u/mkd890)\
**Post date:** [10 February 2020 12:52 UTC](https://reachback.builtintelligence.com/t/nec-ecc-fail-to-reply-quotation-by-project-manager/5604/1 "2020-02-10T12:52:18Z")

</div>

The Project Manager fails to reply a quotation within the time allowed. Can Contractor notifies the Project Manager the quotation is deemed to be accepted?

---

<div class="post-metadata">

**Author:** ![Glenn\_Hide](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/glenn_hide/32/476_2.png) [@Glenn\_Hide](https://reachback.builtintelligence.com/u/Glenn_Hide)\
**Post date:** [10 February 2020 12:55 UTC](https://reachback.builtintelligence.com/t/nec-ecc-fail-to-reply-quotation-by-project-manager/5604/2 "2020-02-10T12:55:20Z")

</div>

The Contractor first has to notify (in writing) the lack of response, and after a further two weeks of silence only then would it be deemed accepted.