# NEC ECC: Defined Cost - Furlough Top Up Payments

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-defined-cost-furlough-top-up-payments/5789>\
**Category:** SOCC SSOCC\
**Created:** [23 April 2020 09:35 UTC](https://reachback.builtintelligence.com/t/nec-ecc-defined-cost-furlough-top-up-payments/5789 "2020-04-23T09:35:21Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![xfinns](https://avatars.discourse-cdn.com/v4/letter/x/54ee81/32.png) [@xfinns](https://reachback.builtintelligence.com/u/xfinns)\
**Post date:** [23 April 2020 09:35 UTC](https://reachback.builtintelligence.com/t/nec-ecc-defined-cost-furlough-top-up-payments/5789/1 "2020-04-23T09:35:21Z")

</div>

If a Contractor pays any discretionary top up to a furlough amount paid by the Government, is this recoverable as Defined Cost e.g. as a component of wages and salaries paid to People?

Under NEC, the Contractor has a duty to react competently and promptly to a compensation event, taking reasonable steps to mitigate its impact (time and cost). Any Defined Cost and time due to the event should be reasonably incurred.

Clause 52 confirms that Contractors take cognisance of all discounts, rebates and taxes which can be recovered e.g. furlough recovery from Government would reduce Defined Cost.

Furlough cannot be imposed on a Contractor’s employees i.e. it is achieved with their agreement. The Contractor offering a top up may have been the influencing factor to an individual(s) and to their agreement i.e. ability of the Contractor to mitigate cost via furlough may not have been possible without the top up offering.

Thoughts welcomed.

---

<div class="post-metadata">

**Author:** ![Jon\_Broome](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/jon_broome/32/192_2.png) [@Jon\_Broome](https://reachback.builtintelligence.com/u/Jon_Broome)\
**Post date:** [23 April 2020 09:46 UTC](https://reachback.builtintelligence.com/t/nec-ecc-defined-cost-furlough-top-up-payments/5789/2 "2020-04-23T09:46:02Z")

</div>

No, it is not recoverable because furloughing means that the employee must stop all work, except in a fe circumstances such as

- training
- essential duties as a director of a company.

Defined Cost is included “only if it is incurred in order to Provide the Works” - see opening para in NEC4 ECC, but there is similar statement in NEC3 ECC.

The 20% top-up is not being incurred to Provide the Works, therefore it is not a Defined Cost.