# NEC ECC: Defects Date

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-defects-date/4362>\
**Category:** Testing and Defects\
**Created:** [21 November 2017 17:49 UTC](https://reachback.builtintelligence.com/t/nec-ecc-defects-date/4362 "2017-11-21T17:49:56Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![turleya](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/turleya/32/87_2.png) [@turleya](https://reachback.builtintelligence.com/u/turleya)\
**Post date:** [21 November 2017 17:49 UTC](https://reachback.builtintelligence.com/t/nec-ecc-defects-date/4362/1 "2017-11-21T17:49:56Z")

</div>

Should the Defects Certificate still be issued at the Defects Date if the procedure outlined in Clauses 44.1 and 44.2 is underway but not been concluded?

---

<div class="post-metadata">

**Author:** ![Andrew\_W-I](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/andrew_w-i/32/151_2.png) [@Andrew\_W-I](https://reachback.builtintelligence.com/u/Andrew_W-I)\
**Post date:** [22 November 2017 08:56 UTC](https://reachback.builtintelligence.com/t/nec-ecc-defects-date/4362/2 "2017-11-22T08:56:46Z")

</div>

The Supervisor is obliged to issue the Defects Certificate either at;

- the defects date,  
or
- the end of the last defects correction period, if a later date.

Any outstanding contract administration procedures should not affect the issuing of the certificate, so in response, yes it should still be issued.

Although a compensation event is not notified after the defects date, the matter in question under clause 44 is not a compensation event, as stated under clause 60.1(1).