# NEC ECC: Contract Date

**URL:** <https://reachback.builtintelligence.com/t/nec-ecc-contract-date/5194>\
**Category:** Time\
**Created:** [29 July 2019 17:40 UTC](https://reachback.builtintelligence.com/t/nec-ecc-contract-date/5194 "2019-07-29T17:40:30Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![KevinMorley](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/kevinmorley/32/112_2.png) [@KevinMorley](https://reachback.builtintelligence.com/u/KevinMorley)\
**Post date:** [29 July 2019 17:40 UTC](https://reachback.builtintelligence.com/t/nec-ecc-contract-date/5194/1 "2019-07-29T17:40:30Z")

</div>

Identified and defined terms 11.2 (4) The Contract Date is the date when this contract came into existence.

is this the date when both parties have signed the contract? or when the Employer has accepted the Contractor’s offer by issuing the contract to him to execute?

---

<div class="post-metadata">

**Author:** ![stevencevans](https://dub1.discourse-cdn.com/flex013/user_avatar/reachback.builtintelligence.com/stevencevans/32/521_2.png) [@stevencevans](https://reachback.builtintelligence.com/u/stevencevans)\
**Post date:** [29 July 2019 21:47 UTC](https://reachback.builtintelligence.com/t/nec-ecc-contract-date/5194/2 "2019-07-29T21:47:39Z")

</div>

I’m not a big fan of this particular definition as contracts can come into existence in many ways.

You will need to apply the law on contract formation to establish when a particular contract came into existence. It could be when the parties sign the contract or it could be when one party makes an offer which is accepted by the other (such acceptance could be by conduct).

In your example, it would be when the Employer has accepted the Contractor’s offer, but more would likely be needed than just sending the contract to be signed as that may be seen as a counter offer.

Each will turn on the particular facts.